Chilli Wilson – Extra notes – Group 3 (Millau)

It should be noted that the materials to be implemented in our bridge  design would be steel for the piers, pre-cast reinforced concrete elements for the bridge and steel tension cables connecting the piers to the bridge (see pictures of Day 4).

It is well known that steel is a material that performs especially well in tension therefore the decision to use that as tension cables. The thinking behind the use of concrete for our  walkway, was that the bridge would be under a heavy traffic flow, as many University students will be using this bridge as a safer way to traverse either side of Lewes road to connect the Moulscoomb campus of the University of Brighton. With such heavy demand, it was decided a dense and solid material for our bridge was needed and reinforced concrete became our material of choice.

DESIGN WEEK 2016

GROUP 3!

Day 1: MONDAY 7TH NOVEMBER 2016

On the first day of this project I was really excited to learn about the variety of techniques and designs associated with making Bridges. We were placed in groups of three  of Brighton’s own University students and three Hazelwick students but this week only involved two Uni students Chris and Chilli and three Hazelwick students including myself, Tracey and Lewis. There was a small presentation about different foot / cycle Bridges and how they are reinforced and the importance of reinforcements such as being cable-Stayed. As a group we exchanged contact details and talked about the task, the five of us later went out to take pictures of where this Bridge is going to be made and positioned. We discussed the requirements of having suitable access for everyone going to PB or the university buildings also considering the height requirements. Returning back to the drawing room, a lecture was held about different types of Bridges e.g. Truss Bridges for example; along with their mechanical properties and the need for forces to be balanced.

 bridge

Day 2: WEDNESDAY 9TH NOVEMBER 2016

The Second day involved the groups working in the Design Studio. This is where we discussed out the plan of action for producing the model of the Bridge and surrounding buildings. We gathered card, dowel, foam board, blades and glue to use as we build our structure. We were in the studio all day, creating and recreating buildings that were out of scale from error or thick cardboard; but we worked as a team to try and get the model done. We all had chosen tasks for each other to do; for example Lewis traced footprints of the buildings whilst Tracey and I cut out the cardboard. Chris organised the poster for our presentation on Friday whilst Chilli helped the rest of us with measuring the heights for the models of the university buildings.

 20161109_114622

Day 3: FRIDAY 11TH NOVEMBER 2016

Before presentations, myself and the rest of the team where in the studio where we hot glued string onto the decking of our Bridge model which represents the supports. We also added the finish touches to the model and went back to the Drawing room. There we discussed the important aspects of our ideas that we needed to get across to the listeners before the presentations began at 11:00am. The presentation went exceptionally well, we finished more or less exactly on time using the full 10 minutes.

2016-11-11-10-06-04

 

 

 

 

Design week- day 3

The majority of day 3 was spent creating a scale model representation of the bridge, which our Brighton university teammates had designed during day two. We did this using card board and foam board.

One of the main concerns when modeling was making sure the bridge was in scale with the plan view map 1:100. Also using the measurements of building we began creating a topographic map, which featured surrounding building within the university campus.

snapchat-6776171656250316733

An issue we did face was picking the correct scale, to represent the changes in ground level and building elevation.

Chilli Wilson – Group 3 (Millau) – Day 1

The first day saw the each of our members converge as a group; me, Chris, Tracey, Lewis and Maisie after we had converge as a group we were briefed on our task for the week: To design and produced a scale model of a cyclist/pedestrian  bridge, that connected the east side of Lewes Road to the west side thus connecting the whole of the Moulscoomb  campus of the University of Brighton.

After we had a lecture on the different constructions of bridges, such as truss bridges, cable-stay bridges,etc, we had a site visit to the entrance of Mithras house which illustrated the height difference from the entrance of Mithras house to Lewes road:

2016-11-07-12-03-56

On the way towards Mithras house I noticed the the amount of trees and other protected structures such as cameras and traffic lights, which meant that our bridge piers and location would be dictated by the location of these structures.

This identified the design parameters set up for our group to design a bridge to fit the brief in Day 2.

Chilli Wilson – Group 3 (Millau) – Day 5

On day five, we were instructed  that we were presenting our bridge design in the drawing studio.

Even though we were told that presenting would commence at 11AM, our group arrived at 9AM, enabling us to apply any finishing details to the model. After I had printed off an A1 print of our poster, we transported the chipboard base which held our different scale-models.

2016-11-11-13-17-53

2016-11-11-13-18-07

Chilli Wilson – Group 3 (Millau) – Day 4

With the topography of the site completed in day three, me and Chris could complete constructing the 1:1000 scale model of our sky walk.

2016-11-11-11-08-44

2016-11-11-10-06-04

Once the 1:1000 scale model was built we could focus on fabricating a 1:200 model of a section of the walkway :

bridge-sketch02

 

 

However, upon construction we discovered that the length of the walkway between the two piers is too long to be supported sufficiently, it would require a steel truss  that is so large that a 5.7m of minimum road clearance would not be possible with this design.

To combat this problem a column, double the height of the piers at 24m, was offset to the bridge with tension wires to support the middle of the bridge:

bridge-sketch032016-11-11-10-07-54

With the 1:200 model fabricated we could now focus on the 1:50 scale model of our detail of our design, this model illustrated the joint between the walkway and the “pod” pier and highlights the prefabricated nature of our design:

2016-11-11-10-06-40

2016-11-11-10-06-30

With these three models created we could now focus the morning of day five on practising what each individual will present in our presentation.

 

Chilli Wilson – Group 3 (Millau) – Day 3

As stated in the last Blog post, with the dimensions of our design  calculated, we could commence work on constructing  the model of our bridge. Once we had convened as a group, we set about to the heavy engineering wing to create a scale model of our design.

Once there, me and the Hazelwick students were tasked with translating the topographical information we had gather from in front of Mithras house:

s16111113350

This had to follow an A1 1:1000 map of the site we had printed off the day before:

20161109_140127

20161109_114622

Once the topography in front of Mithras house had been successfully rendered in to the model-space we set about constructing Mithras House, Watts building and Cockroft building. The erection of these buildings in the model space enabled our sky-walk to be viewed in context within the Moulsecoomb campus.

With the completion of these buildings and the topography, we could commence constructing our model of the bridge at scale 1:1000,  a close-up model of the walkway at scale 1:200 and a 1:50 scale model of a the joint between a walkway and a “pod”, where the walkways converge.

 

Chilli Wilson – Group 3 (Millau) – Day 2

Yesterday saw the formation of our team and the identification of our outlines as stated in the brief.

Today saw us visually communicate our initial ideas for our bridge design through the use of sketches:

saldrich_li16110811010-1

As stated in the brief, we must create a bridge that links university buildings either side of the Lewes Road, therefore, we deiced initially to design a bridge that resembled the shape of a algebraic “X”. This design consisted of a central pod with two sets of bowed walkways connecting the pod to either side of Lewes Road. The advantage of having two separate pathways on either side of the road meant that local residents and other members of the public could use the bridge not just University of Brighton Students.

However, we decided that to achieve a more effective linking with the university buildings, expansion of this core idea was needed to fulfil this aim:

saldrich_li16110811020

By enabling access to not just Preston Barracks, but Watts Building, the Heavy Engineering development and Cockroft building, we had achieved this goal.

But doing this meant that we had to manipulate and extended our original “X” shape, with the inclusion of long, straight pathways and the inclusion of numerous support columns :

saldrich_li16110817190

With the bridge design finalised,  dimensions of the bridge could be calculated:

saldrich_li16110817180

With the dimensions of our bridge calculated we can start building a scale model of our bridge and compiling our presentation, in Day 3.

 

Design week 2016: Learning through making – Day one

For a third year in a row, Brighton university has hosted design week. During the course of the week university students work in conjunction with first year a-level students from Hazelwick school, studying 3d design.

This year the task given revolves around pedestrian and cycle bridges. Our client is Brighton university, who ask us to come up with an innovative bridge designs which we will model and present. One of the main points in the brief is that we link conveniently and practically two parts of Moulsecoomb campus on both sides of A27, Lewes Road.

Project brief

copy-of-snapchat-7747257724546070942

 

Shorty after being presented our task, we set out in our allocated groups to have a look at the A27, Lewis road; and create ruff sketches and plans.

b1

View of Moulsecoomb campus

b2