Closing Blog

Hove Gardens has been a pleasure to study and having an arrange site visit helped me source photos of on going work. Although this is a fairly major project and I will not be able to see the project be completed, I this past weeks have taught me a lot on how work goes on in and around site.

The workload that is currently underway are concrete pouring for floors and walls, as well as deliveries of pods and fitting these pods into the building using cranes.

 

 

Here are references that were used in this blog:

https://www.hove-gardens.com/wp-content/uploads/2021/08/Hove-Gardens-2-Public-Consultation-Boards_db-min.pdf

https://rg-group.co.uk

https://www.brightonandhovenews.org/2020/09/02/councillors-approve-67m-18-storey-hove-gardens-scheme-for-216-flats/

https://www.brighton-hove.gov.uk

https://www.youtube.com/watch?v=UWlnIa2tmmk

Pods

One major part of this project was ordering the ensuite/bathrooms for the build to rent homes. These were supplied by a company in Hull that come as a fully finished pod. Inside these cuboid pods, are a full fitted bathroom, tiled, with mirrors, toilet, and multi bath and shower all plumbed and ready to be installed into the building.

The pods where delivered wrapped in an orange protective film, and on a steel frame bottom. this makes it easy for the crane to manoeuvre the object.

A temporary platform is bolted on the side of the building where the crane can lower each pod into position on each floor.

 

Phase 2 Next steps

As phase 1 is deep into its constructional build, Phase two is still in the works to commence. The initial consultation with BHCC first underwent in July 2021, with a public consultation following in the later august 2021. the application for submit planning was sent off in Autumn 2021 with an approved application by the council in Spring 2022.

Now all is approved, and set to start, construction will commence this Summer of 2022, hoping for completing in Spring 2024. Once completed, the first tenants for phase 2 will be able to move in for Summer 2024.

 

 

 

References:

https://www.hove-gardens.com/wp-content/uploads/2021/08/Hove-Gardens-2-Public-Consultation-Boards_db-min.pdf

Temporary Bracing

As this Project comes under a high rise building, majority of the build is waiting for concrete to cure in order to build upwards. to help speed up this process, RG are using temporary bracing to strengthen the integrity of the building’s structure. once concrete on lower levels have cured, then the temporary bracing can be removed and placed on levels above that have been poured more recently. Currently the East tower on site has reached its 9th storey, with the platform in place starting from the 8th.

RG must balance the management of curing concrete and project time and scheduling. They do not want to fall behind on schedule due to unsettled concrete, but also do not want to tush the project and suffer the consequences of fallen, unshared concrete. Which can lead to extreme situations such as collapses.

Site Planning and management

At this current stage of the project, there is limited space to manoeuvre around site or for materials to be stored. this creates pressure on the team to get work done, so new storage locations can be freed up. This can also produce a high level of risk and caution when moving on site as some areas may be cluttered with materials.

The site office is located on the East of the site, being a double storey office. however, this is still very small, creating an issue for all members of RG to work in the office. So a selection of extra office space is located offsite, north of Hove Train Station.

Phase 1

The next objective for the Hove Gardens project is to aim to get the two towers up and structured, as well as increasing the storeys of the adjacent building below.

Large transit mixers are currently on site, pumping tons of concrete through flexible pipework to wherever the the concrete is needed on site. The cost manager Omar Flint, who is currently on a placement year for RG Group, and studies at University of Brighton, mentioned that part of his job is to calculate how long the pipework needs to be to distribute the concrete around site. He can then go onto calculating the price per metre, to ensure the cost is at a minimum.

when pouring the concrete, a team of men are picking down the concrete to ensure no air is locked inside the concrete. not only does this strengthen the concrete when it sets, but also gives the concrete a flush finish. Steel rods in position to also strengthen each floor and retaining walls in the structure. However, in order to use these, workers must place 20mm spaces across the entirety of each new floor. This prevents the steel rods from being on the face in the concrete structure, avoiding weathering rust to the face of each floor.

 

In order to progress with the project, each previous floor of concrete must set and become strong enough before a further storey can be added above. this is crucial to the integrity of the build as there can not be room for error of a floor collapsing. On the East and West towers of Hove gardens, there are platforms that are temporally bolting to the top of the towers. these are lifted and moved higher by the site cranes when the floor below has cured, ready for the next level of concrete.

 

 

 

Crane Operation

There are two cranes currently based on the site, located East and west sides in order to serve the two towers onsite, alongside the new adjacent building below. The crane arm is positioned in an obtuse angle as the square perimeter of the site is rather narrow. This means there are open roads surrounds the site which the crane cannot overhang.

Before the cranes could be setup, and application was approved by Network Rail as the crane is situation near the Hove railway track. If the machinery were to fall over in any circumstance, it ha the length to land and damage there railway tracks.

Both two cranes are sunken into the foundation of the site and bolted into place, in order to allow the crane to carry have loads. when RG are finished with the cranes, and no longer serve a purpose, the cranes will be unbolted and removed. the leftover area where the crane used to be will then get filled in by concrete.

 

Hove Gardens

Link

Hello, this blog will be detailing an ongoing RG Group site located in Hove, just south of Hove Train Station.

Hove Gardens is the name of this site, which is undergoing phase 1 of its build, with phase 2 approved. The address is 1-3 Ellen Street,  Hove, BN3 3LN.

This post will discuss the project details, as well as a brief overview on each phase of the development.

The site is under management by RG Group who have been outsourced by Watkin Jones Group to complete the project on behalf of another client, this makes Watkins Jones the main client for RG. CJCT are the architects involved in this project, alongside the landscape architects AJM. Traffic and highways consultants for the project are ADL Traffic and highways engineering Ltd. Savills are the planning consultants for Hove Gardens. Public consultants are SEC Newgate, and the heritage consultant is Stephen Levrant Heritage Architecture.

Overview on Phase 1:

Brighton & Hove City Council approved plans for Phase 1 of the project back in October 2020.

The priority objectives for phase 1 is to build 216 build to rent (BtR) homes on a 2003 sqm commercial scale, with two east and west towers, one being 18 storeys, and the other 9 storeys. Lower, adjacent buildings will connect the two towers. Public realm is also focused on being improved by this project.

Overview on Phase 2:

Phase 2 will be an extension of phase 1, by integrating the land directly west to phase 1 location. this will make room for an extra 86 new BtR homes, with included options for affordable homes. The size of phase 2 will be an extra employment floorspace of 360 sqm, making the overall project 2363 sqm.

 

The budget for this project is £60 million GBP with and project vision of bringing local residents together and creating a positive community living experience.

The site first commenced on 21st June 2021 with works first starting a week later on the 28th June 2021. The main milestones for this project include piling to be completed by early September 2021, frame construction period to be December 2021 to April 2022. Also, the Landscaping works are scheduled to commence in the summer of 2022.

The overall project is scheduled to be completed for summer 2023.

The user experience for Hove Gardens include 119 bicycle spaces, improved public realm, with extensive residential amenity spaces distributed around the building. These consist of 4 roof terraces, with an extra being proposed in the second phase of the project.

Hove Gardens will bring many benefits when completed, such as providing needed new homes, in line with the council planning policy, together with new affordable homes in the area. This build will also improve the level of security in the area by providing passive surveillance, this can make local residents feel safe when the project is completed. As well as this, the local economy will see an improvement as new residents will boost local spending. An increase in the local biodiversity as new trees, shrubs and bird boxes will be implemented at near the end of the project.

 

 

References:

https://www.hove-gardens.com/wp-content/uploads/2021/08/Hove-Gardens-2-Public-Consultation-Boards_db-min.pdf