As this Project comes under a high rise building, majority of the build is waiting for concrete to cure in order to build upwards. to help speed up this process, RG are using temporary bracing to strengthen the integrity of the building’s structure. once concrete on lower levels have cured, then the temporary bracing can be removed and placed on levels above that have been poured more recently. Currently the East tower on site has reached its 9th storey, with the platform in place starting from the 8th.
RG must balance the management of curing concrete and project time and scheduling. They do not want to fall behind on schedule due to unsettled concrete, but also do not want to tush the project and suffer the consequences of fallen, unshared concrete. Which can lead to extreme situations such as collapses.